On the morning of 1 April 2026, the Technology and Construction Court handed down a ruling that the construction industry will be discussing for years. In Crest Nicholson v Ardmore, the court granted a Building Liability Order (BLO) that pierced the corporate veil of one of London's most established main contractors — and in doing so, fundamentally changed the risk landscape for every firm operating in the UK built environment.
The Case in Plain English
Ardmore Construction Ltd was the design and build contractor on Admiralty Quarter, a large residential development in Portsmouth built between 2007 and 2009. Post-Grenfell fire safety investigations found serious external wall defects. Crest Nicholson, the developer, took Ardmore to adjudication in May 2025 and won an award of approximately £14.9 million.
Then Ardmore Construction Ltd entered administration — the day before the adjudicator's decision was issued. Convenient timing or not, the practical effect was that Crest was owed £14.9 million by a company that no longer had the assets to pay it.
This is where Building Liability Orders come in. Introduced under sections 130–131 of the Building Safety Act 2022, BLOs allow the High Court to impose a liability held by one company onto associated companies in the same corporate group — even companies that had nothing to do with the original build. The court does this when it considers it just and equitable.
The TCC agreed it was just and equitable. BLOs were granted against seven Ardmore-linked entities: Ardmore Construction Group Ltd, Ardmore Group Ltd, Ardmore Group Holdings Ltd, Paddington Construction Ltd, Ardmore Fitout Ltd, Celebration Homes Ltd, and Byrne Properties Ltd. Every one of those companies was suddenly on the hook for £14.9 million.
The court also issued an 'anticipatory' BLO — a forward-looking order attaching future unquantified liabilities to those associated companies before the underlying trial was even concluded. That had never been done before.
Why This Matters Beyond the Headline
The conventional wisdom in construction has long been that project risk can be contained within the contracting entity — typically a subsidiary or special purpose vehicle set up for that specific contract. If a defect claim emerges years later, you go after the contracting company. If it has been wound up or is undercapitalised, you lose. The group survives.
The Ardmore ruling closes that escape route. Courts are now willing to look at the whole group structure, ask who benefited, who exercised control, and who has assets — and then make those entities pay. The TCC made clear that BLOs are not just tools against thinly capitalised SPVs. They apply in much wider circumstances, wherever the court considers pursuit of associated companies to be just and equitable.
For the construction industry, this has cascading consequences. Clients and funders are now asking different questions when appointing contractors. Insurers are repricing group-wide exposure. And subcontractors are left wondering: when my main contractor goes under, what does this mean for my unpaid applications?
The Subcontractor Position When a Tier 1 Falls
Let's be direct. If Ardmore's construction arm enters administration, subcontractors do not benefit from BLOs. BLOs are a tool for developers and building owners pursuing contractors, not a mechanism for subbies to recover their money.
What you face as a subcontractor when a tier 1 goes under is the unsecured creditor queue — and that queue is long and slow. Your unpaid applications, your retention, your materials on site: all of it becomes an unsecured claim in the insolvency. The Housing Grants, Construction and Regeneration Act gives you adjudication rights, but adjudicating against an insolvent company produces an award you cannot collect.
What the BLO ruling does change, indirectly, is the risk profile of every major contractor in the UK. If group holding companies can now be pursued for legacy building safety claims, the financial pressure flows upward through group structures that previously felt insulated. Live projects under a financially pressured group face heightened programme and payment risk. That risk lands on subbies first.
What the Ardmore Story Actually Tells You About the Market
Ardmore's situation is not a one-off. Construction remains the sector with the highest number of insolvencies in England and Wales — 3,827 cases in the year to March 2026, around 17% of all corporate failures. BLO exposure is now being cited alongside geopolitical cost pressures, the Iran conflict supply chain shock, and persistent thin margins as a structural risk for any contractor with legacy residential work completed between 1992 and 2022.
The question for every subcontractor is not whether this could happen to your main contractor. The question is whether you have the commercial intelligence to know when it is happening — and whether you are positioned to act before the administration notice lands.
SubTrada exists, in part, to address that intelligence gap. Knowing who you work for, what their financial health looks like, and whether they are diversifying or concentrating risk is not a luxury. In 2026, it is a basic requirement for any subcontractor serious about staying solvent.